The scaffold should be
erected in continuous
sequence starting from
the corner of the
structure or the highest
ground level point. The
ground must be
compacted first.
Four base jacks are
adjusted to the same
height.
|
|
 |
Hold standards upright to allow additional ledgers
to be fitted first at 90° to the standard. Connect
next row of standards and jacks to complete the
first row which must be properly aligned, plumbed
and squared.
|